Friday 31 August 2012

Piering & Plumbing done

Another step forward this week.
Yesterday the piering was completed and today the plumbing. So hopefully that means the slab might happen next week.





Friday 24 August 2012

Sunday 19 August 2012

Block ready for site start

This week saw the arrival of a portaloo and on friday we found the block fenced off. No official word on when we will start, but I am guessing it will be soon.

Saturday 4 August 2012

Construction certificate issued

We have finally had some progress this week. Our final construction plans were received as well as all our other paperwork which has now been signed off. Advised on Thursday our construction certificate has been issued. Our file is now off to the construction team and hopefully we will start in approx 3 weeks.